Core Path · L3.7.05

Key risk indicators in practice

12 minKey risk indicatorsThresholdsPercentilesEscalationEarly warning

By the end you will be able to

  1. 1Choose indicators for a key risk, and tell leading, current and lagging ones apart.
  2. 2Calibrate amber and red thresholds at percentiles of a quiet history, and explain the trade-off between early warning and false alarms.
  3. 3Measure whether a KRI led a loss, and by how many days.
  4. 4Escalate a KRI breach to the right forum, and say what a warning can and cannot do.

Why it matters

RiskAtoms Bank's phishing test click rate went red in January 2025. On 2 April criminals used phished mailboxes to redirect client payments, and the bank lost £5.1m. Its platform availability went red in August; on 14 October the payments platform went down for 31 hours. Two indicators warned, 61 and 44 days ahead. Complaints, by contrast, went red only after the outage. The difference between those indicators is what this lesson is about.

Core explanation

Choosing, calibrating and acting on indicators

L2.4.06: Key risk indicators introduced KRIs with green, amber and red thresholds, and L3.3.17: Early warning, watchlists and workout showed early-warning indicators for borrowers. Operational risk uses the same idea for people, processes and systems. RiskAtoms Bank watches ten:

RiskAtoms Bank's KRIs, thresholds and status in December 2025 (illustrative)
IndicatorUnitAmberRedDec 2025First redKey risks
Failed outbound paymentsper 10,000 payments≥ 15.0≥ 25.06.9 GreenOct 2025R03, R13
Payments platform availability% of service hours< 99.90< 99.5099.94 GreenAug 2025R03
Operations staff turnover% a year (rolling)≥ 15.0≥ 20.013.3 GreenneverR07, R16
Critical security patches overduecount over 14 days≥ 5≥ 103 GreenAug 2025R01, R03
Phishing test click rate% of staff tested≥ 5.0≥ 8.03.7 GreenJan 2025R01, R02, R12
Customer complaintsper 1,000 accounts a month≥ 2.00≥ 2.501.45 GreenOct 2025R09, R10
Reconciliation breaks open over 30 dayscount≥ 20≥ 408 GreenneverR07, R14
Critical third-party SLA breachescount in month≥ 3≥ 50 GreenneverR04, R05
Material models overdue for validation% of material models≥ 5.0≥ 10.07.7 AmberneverR15
Control actions past due% of open actions≥ 10.0≥ 20.025.0 RedDec 2025none

Choosing: lead, current or lag

A leading indicator measures a cause; a current one measures the exposure now; a lagging one counts the damage. The Institute of Operational Risk's guidance is blunt: truly leading indicators are rare, and a trend on its own does not make an indicator leading. A good KRI is linked to a named risk in the RCSA, measured reliably and cheaply, expressed as a rate where volumes change, and few enough that someone reads it.

Sort itLeading, current or lagging?

Six of the bank's indicators and one more. Classify each for the risk it is linked to.

  • Phishing test click rate (% of staff tested), for account compromise and payment fraud

  • Critical security patches overdue more than 14 days, for ransomware and failed changes

  • Operations staff turnover, for processing errors and internal fraud

  • Payments platform availability (% of service hours), for a major outage

  • Failed outbound payments per 10,000, for payment processing errors

  • Customer complaints per 1,000 accounts, for poor outcomes and conduct risk

  • Net operational losses booked this month

Calibrating: percentiles of a quiet history

Calibration sets where green ends. A common start is the past: put amber where the indicator is worse than most of a quiet period, and red where the risk would leave appetite. The IOR suggests collecting at least six months of data, preferably a year, before setting the first thresholds. For the book's KRIs the calibration window is January to October 2024, ten months before any of the leading indicators left green. A percentile (M-C09: Quantiles) of that window says how unusual a reading is. Set amber at the 90th percentile and, by construction, about one quiet month in ten would have been amber: a false alarm. Set it higher and the alarms stop, but the warning comes later.

Percentiles of January to October 2024 against the book's amber thresholds
IndicatorWorst quiet month90th percentileBook's amber
Failed outbound payments11.310.8515.0
Payments platform availability99.9299.93899.90
Operations staff turnover13.713.4315.0
Critical security patches overdue33.05
Phishing test click rate4.24.115.0
Customer complaints1.731.6312.00
Reconciliation breaks open over 30 days1515.020
Critical third-party SLA breaches22.03
Material models overdue for validation4.14.015.0
Control actions past due9.69.0610.0

Every book threshold sits beyond the worst quiet month: the bank chose few false alarms. The calibration notes say how: amber near the 90th or 95th percentile of a longer history for phishing and failed payments, the agreed service level for availability, the patch policy for patches. Whole-number counts are awkward: overdue patches had a value of 3 in five of the ten quiet months, so an amber at the 90th percentile, 3, would have raised 5 false alarms.

Did it lead? Measuring the warning

A KRI earns its place if it warns early enough to act. The lead time is counted from the last day of the first amber or red month, when the value is reported, to the day of the loss:

Phishing test click rate · first amber Nov 2024, first red Jan 2025, 61 days before the business email compromise fraud

Jan 2024Jan 2025Dec 2025

Outlined: Apr 2025, the business email compromise fraud

Critical security patches overdue · first amber May 2025, first red Aug 2025, 44 days before the payments outage

Jan 2024Jan 2025Dec 2025

Outlined: Oct 2025, the payments outage

Payments platform availability · first amber Jul 2025, first red Aug 2025, 44 days before the payments outage

Jan 2024Jan 2025Dec 2025

Outlined: Oct 2025, the payments outage

Failed outbound payments · first amber Aug 2025, first red Oct 2025, in or after the month of the payments outage

Jan 2024Jan 2025Dec 2025

Outlined: Oct 2025, the payments outage

Customer complaints · first amber Oct 2025, first red Oct 2025, in or after the month of the payments outage

Jan 2024Jan 2025Dec 2025

Outlined: Oct 2025, the payments outage

Three indicators led: phishing clicks by 61 days from red (123 from amber), availability by 44 days (75 from amber), overdue patches by 136 days from amber. All three were green for the whole of the first ten months. Failed payments turned amber in August but red only when the outage hit, and complaints turned red only afterwards. Hover over a month to see its value.

Escalating

A threshold is only useful if it triggers something. Each status has an owner and a deadline, and escalation moves a breach up as it worsens or lasts. The IOR's guidance distinguishes a touch trigger, escalated at once, from a repetitive-touch trigger, escalated if the breach persists into the next report. RiskAtoms Bank's ladder (illustrative):

ExploreThe bank's escalation ladder

Click a status to see who hears about it and what they must do.

Green

Monitors; no report beyond the monthly pack.

In the two years, 3 indicators stayed red for two months or more and so reached the board risk committee: payments platform availability, critical security patches overdue, phishing test click rate.

Illustrative dataRiskAtoms Bank plc's operational risk book

The same £67bn bank as Modules 3.5 and 3.6, at 31 December 2025, in pounds: ten years of internal loss events of £10,000 or more (2016–2025), an RCSA of 17 key risks and 29 controls, ten key risk indicators over 24 months, seven workshop scenarios and five important business services. Every event, person, supplier and figure is made up for teaching; none is any bank's data. The same book runs through every lesson in Module 3.7, so the figures agree.

The KRI values, thresholds and calibration notes are the book's; some months are set by hand to tell the story. The escalation ladder is an illustrative extra.

The formal version

The status rule is the one from L2.4.06: Key risk indicators: green below amber AA, amber from AA, red from RR, with the inequalities reversed when lower is worse. Calibration uses a quantile of the window's nn values, sorted x(1)≤⋯≤x(n)x_{(1)} \le \cdots \le x_{(n)}, by linear interpolation (M-C09: Quantiles):

h=1+(n−1) pQp=x(⌊h⌋)+(h−⌊h⌋)(x(⌊h⌋+1)−x(⌊h⌋))A={Qphigher is worseQ1−plower is worse\begin{aligned} h &= 1 + (n-1)\,p \\ Q_p &= x_{(\lfloor h \rfloor)} + \bigl(h - \lfloor h \rfloor\bigr)\bigl(x_{(\lfloor h \rfloor + 1)} - x_{(\lfloor h \rfloor)}\bigr) \\ A &= \begin{cases} Q_p & \text{higher is worse} \\ Q_{1-p} & \text{lower is worse} \end{cases} \end{aligned}

For the phishing click rate, n = 10 and p = 0.9:

h=1+9×0.9=9.1Q0.9=x(9)+0.1 (x(10)−x(9))=4.1+0.1×(4.2−4.1)=4.11%\begin{aligned} h &= 1 + 9 \times 0.9 = 9.1 \\ Q_{0.9} &= x_{(9)} + 0.1\,\bigl(x_{(10)} - x_{(9)}\bigr) = 4.1 + 0.1 \times (4.2 - 4.1) = 4.11\% \end{aligned}

The share of quiet months above QpQ_p is close to 1−p1 - p, so the false-alarm rate is chosen when pp is. The lead time is counted in days from the reporting date of the first red month, tredt_{\text{red}}, to the loss:

Δ=tloss−tred=2 Apr 2025−31 Jan 2025=61 days\Delta = t_{\text{loss}} - t_{\text{red}} = \text{2 Apr 2025} - \text{31 Jan 2025} = 61\ \text{days}

Try it

Pick an indicator, set amber at a percentile of the quiet months and choose a red level. Can you find a setting for the phishing KRI that warns earlier than the book's, and how many false alarms does it cost? What happens to overdue patches at the 90th percentile?

Try itCalibrate a key risk indicator

Jan 2024Jan 2025Dec 2025

Outlined: Apr 2025, the business email compromise fraud

Amber from4.110
False alarms in the 10 quiet months1
First amberJul 2024
First redJan 2025
Warning from first amber245 days
Warning from first red61 days
Amber months / red months4 / 3
Book's thresholds5.0 / 8.0 (0 false alarms)

Illustrative book. Warning is counted from the last day of the month the value is reported to the day the loss happened. A false alarm here is any amber or red month in January to October 2024, when nothing was building up. For platform availability lower is worse, so the 90th percentile in the bad direction is the 10% quantile. Book thresholds: amber about the 90th percentile of the last two years' tests; red at twice the target.

Worked example

Calibrating and judging the phishing KRI

At the start of 2024 the Chief Information Security Officer asks the second line to set thresholds for the phishing test click rate. Work each step before you open it.

From quiet history to a warning that was used, or not

Step 1 of 5
  1. 1

    The window

    Ten monthly tests, January to October 2024, sorted: 2.8, 2.8, 3.1, 3.2, 3.4, 3.4, 3.7, 3.7, 4.1, 4.2 (% of staff who clicked). Median about 3.4%; worst month 4.2%.

Regulatory lens

The 2021 Basel principles list metrics among the tools for identifying and assessing operational risk: simple indicators or more advanced exposure models that give early warning and are tracked against thresholds or limits (paragraph 35(e)), and they ask for regular monitoring and reporting of the risk profile at board, senior management and business levels (Principle 8). KRIs do not enter the standardised capital calculation, which uses business size and the loss history of L3.7.03: Loss data (M4.4: Counterparty, operational and large exposures), but supervisors expect them to link to the appetite (L3.7.02: The operational risk framework). Indicators for important business services return in L3.7.15: Operational resilience.

Spark Atoms

Spark AtomTruly leading indicators are rare
The Institute of Operational Risk's 2010 sound practice guidance on KRIs warns that truly leading indicators are rare, that many indicators are both lagging and current, and that trending on its own does not make an indicator leading. Its examples of leading ones are things like the average length of delays in executing activities and the number of limit breaches: signs that the controls are under strain before anything breaks.
Spark AtomHard-coded months
The book's three leading KRIs were written by hand to lead its two losses; the other months are seeded noise. Real indicators are rarely this tidy. A bank should test each KRI the way this lesson did: count its warnings, its false alarms and its misses against the loss data, and drop the ones that never warn.

Key takeaways

  • A KRI is linked to a key risk, measured reliably, and has thresholds that trigger action; leading indicators are the most useful and the rarest.
  • Calibrate amber at a percentile of a quiet history: at the 90th percentile about one quiet month in ten is a false alarm. For phishing that is 4.11%; the bank chose 5%.
  • Higher thresholds mean fewer false alarms and later warnings; red is usually set where the risk would leave appetite.
  • Measure a KRI by its lead time: phishing clicks warned 61 days before the fraud, platform availability 44 days before the outage; complaints only after.
  • Escalation turns a status into a decision; a warning reduces a loss only if someone acts on it in time.

Reaction

Check what stuck

Question 1 · objective 2

The phishing click rate in the ten quiet months, sorted, was 2.8, 2.8, 3.1, 3.2, 3.4, 3.4, 3.7, 3.7, 4.1, 4.2 (%). Using linear interpolation, h = 1 + (n − 1)p, what is the 80th percentile, in %?

%

Question 2 · objective 1

Customer complaints turned red in October 2025, the month of the payments outage, and not before. What kind of indicator is that here?

Question 3 · objective 3

Platform availability was first red in August 2025 (reported on 31 August). The payments outage happened on 14 October 2025. How many days of warning did the red give?

days

Question 4 · objective 2

A bank sets a KRI's amber threshold at the 90th percentile of ten quiet months. Roughly how many of those quiet months would have been amber?

Question 5 · objective 2

For platform availability, where lower is worse, at which quantile of the quiet months should a '90th percentile' amber sit?

Glossary

Key risk indicator
Key risk indicator (KRI): a number measured regularly, with thresholds, that shows whether a key risk is growing.
Leading indicator
Leading indicator: measures a cause, so it moves before the loss.
Current indicator
Current indicator: measures the exposure as it is now, such as how often a service is down this month.
Lagging indicator
Lagging indicator: measures the damage after it has happened, such as complaints or losses.
Calibration
Calibration: choosing an indicator's amber and red thresholds, from history, targets and appetite.
Calibration window
Calibration window: the past period whose values are used to set thresholds; ideally a quiet one.
False alarm
False alarm: an amber or red reading when nothing is building up. Too many and people stop listening.
Lead time
Lead time: the days between a KRI's warning and the loss it warned of.
Escalation
Escalation: passing a breach to a more senior forum, with a deadline, as the status gets worse.
Touch and repetitive-touch triggers
Touch and repetitive-touch triggers: a breach escalated as soon as it happens, or only if it persists into the next reporting period.

Deep Dives & Origins

Deep Dives

  • Institute of Operational Risk, Key Risk Indicators, Operational Risk Sound Practice Guidance, IOR, November 2010: choosing, calibrating and reviewing KRIs. Introductory.
  • Basel Committee on Banking Supervision, Revisions to the Principles for the Sound Management of Operational Risk, BIS, March 2021, paragraph 35(e) and Principle 8. Intermediate.

Origins

  • Institute of Operational Risk, Key Risk Indicators, Operational Risk Sound Practice Guidance, version 1, IOR, November 2010, sections 3 to 5.
  • Basel Committee on Banking Supervision, Revisions to the Principles for the Sound Management of Operational Risk, Bank for International Settlements, 31 March 2021.